Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.
Central Act · India · Part Vii — Tariff
Section 63 Determination of tariff by bidding process
Electricity Act, 2003 · Edition: Archived India Code text (2021 dataset) · Assent 26th May, 2003
Judgments on Section 63
LOK 2017 (4) SC 119 · Supreme Court of India
Energy Watchdog v. Central Electricity Regulatory Commission and Ors. Etc
LOK 2016 (12) SC 1415 · Supreme Court of India
Haryana Vidhyut Prasaran Nigam Ltd. v. Haryana Electricity Regulatory Commission & Anr.
LOK 2016 (12) SC 810 · Supreme Court of India
All India Power Engineer Federation & Ors. v. Sasan Power Ltd. & Ors. Etc
Subject–
Judges–
ActsElectricity Act, 2003, Indian Contract Act, 1872, 29, 61, 62, 63 and 125, Electricity Act, 2003, 62 and 63, Indian Contract Act, 1872