(1) Every owner shall, on completion of development or redevelopment of land or construction or reconstruction or addition or alteration of b uilding, a s per the per mit iss ued to him, submit a completion certificate certified and signed by him to the Secretary in the form in Appendix E1 together with sufficient copies of plans and drawings of completed building:
Provided that in the case of bui ldings, other than residential buildings upto two floors with total built-up area not exceeding 150 sq. metres, the completion certificate shall be certified and signed by the owner and registered Institution or Architect or Building Designer or Engineer o r Supervisor also as in Appendix E3 together with sufficient copies of plans and drawings of completed building.
(2) The Secretary shall, on receipt of the completion certificate and on being satisfied that the development or redevelopment of land has bee n effected in conformity with the permit given, issue a development certificate in the form in Appendix F1 along with a copy of the plans duly signed by the Secretary, not later than 15 days from the date of receipt of the completion certificate:
Provided that if no such development certificate is received within the said fifteen days, the owner may proceed as if such a development certificate has been duly issued to him. On the expiry of fifteen clear days from the date of valid application for development certificate, the applic ant shall submit a letter stating that he is liable to get development certificate and now it is deemed to have issued by the authority. All Secretaries of Local Self Government Institutions shall acknowledge the receipt of the letter stat ed in the abo ve paragraph with stamp and date on the same day on the duplicate copy of the letter. This shall be a deemed development certificate.
(3) The Secretary shall, on receipt of the completion certificate and on being satisfied that the construction or reconstruction or addition or alteration has been carried out in conformity with the permit given, issue occupancy certificate in the form in Appendix F2 not later than fifteen days from the date of receipt of the completion certificate:
Provided that , in case the re is deficiency as per provisions of these Rules, in minimum width of mandatory open space/yard after completion of the construction, other than the distance stipulated as per section 383A of the Kerala Municipality Act, 1994 ( 20 of 1994) and sub-rule (5) of rule 81 of these rules, the Secretary may allow a tolerance up to 5% of the minimum mandatory open space/yard to be provided as per these rules or twenty five centimeters, whichever is less, for the building constructed:
Provided further that if no such occupancy certificate is issued within the said fifteen days, the owner may proceed as if such occupancy certificate has been duly issued to him. On the expiry of fifteen clear days from the date of valid application for occupancy certificate, the applic ant shall submit a letter stating that he is liable to get occupancy certificate and now it is deemed to have issued by the authority. All Secretaries of Local Self Government Institutions shall acknowledge the receipt of the le tter stated in the above paragraph with stamp and date on the same day on the duplicate copy of the letter. This shall be a deemed occupancy certificate.
(4) The owner of a building may, if he intends to occupy the building before its completion, apply t o the Secretary for that purpose together with partial completion certificate by the owner and registered Institution /Architect/Building designer/Engineer/ Supervisor in Appendix E2 and E4 respectively, and sufficient copies of plans and drawings of partia lly completed building
(5) Secretary shall ensure the compliance of the provisions of these rules in respect of the partially completed building and on being satisfied that such occupancy will not endanger life, issue occupancy certificate in respect of such partially completed building.