LOK 2026 (11) SC 180 · Supreme Court of India

Power Grid Corporation of India Ltd. v. Tangedco

Equivalent citations: 2026 INSC 1237

ActsElectricity Act, 2003 (Sections 29(4), 79 and 178); Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (Regulations 3(53) and 4(3)(ii))

The Central Transmission Utility claimed transmission tariff for two LILOs on the Tuticorin JV–Madurai 400kV line at the Tuticorin Pooling Station, commissioned in January 2015. The CERC accepted the commercial operation dates and fastened the transmission charges on the generating company until its dedicated transmission line was commissioned on 27.10.2016. The Appellate Tribunal reversed the CERC, holding that the use of the LILOs was not established and that the commercial operation date had not been properly approved. The transmission utility appealed.